Britain Fɔɔra Yɛla Zɛ’an 8 (March Ta Paɛ August 2019)

Britain Fɔɔra Yɛla Zɛ’an 8 (March Ta Paɛ August 2019)

Fɔɔra yɛla zɛ’an wa, ho wan nyɛ Yehowa Sɛɛradoma n malum mɛta ba tigere yile la Britain teŋa poan se’em pɔsɛ March ta paɛ August 2019.

  1. Saazuo Bɔba Maalegɔ Deo (Vidiyo Maalegɔ)

  2. Teŋanɔɔrɛ Bɔba Maalegɔ Deo (Maintenance la Services)

  3. Ɔfisi Tuuma Deo

  4. Gã’aregɔ Zɛ’an A

  5. Gã’aregɔ Zɛ’an B

  6. Gã’aregɔ Zɛ’an D

  7. Gã’aregɔ Zɛ’an E

  8. Gã’aregɔ Zɛ’an Ɛ

  9. Gã’aregɔ Zɛ’an F

March 5, 2019​—Ɔfisi Tuuma Deo

Mabia n boi ko’om tuulegera deo poan tuna.

March 29, 2019​—Teŋanɔɔrɛ Bɔba Maalegɔ Deo

Mabiisi n boi bim kɛ̃’ɛsa tiles insɔɔseŋa poan.

April 10, 2019​—Ɔfisi Tuuma Deo

A worker installs a lattice of lightning rods known as an air termination network. This network is part of a system designed to protect the building from lightning strikes. The worker’s harness is anchored to the roof, allowing him to work safely.

April 16, 2019​—Ɔfisi Tuuma Deo

Mabiisi n duuseri takɔla ti ba dekɛ stickers labelɛ ti nɛreba ta’an tara bamea soŋa. Stickers la wan basɛ ti nɛreba baŋɛ ti la dela deo glass la wan eŋɛ se’em ti ba kan keŋɛ ta sɔ̃’ɛ ba.

April 23, 2019​—Gã’aregɔ Zɛ’an A

Using a closed-circuit television camera, a member of the site-works team checks that newly installed drains are clear and ready for use.

April 23, 2019​—Ɔfisi Tuuma Deo

Karpintadoma n kpa’ari dɔɔrɔ labela dia la laɣesegɔ zɛ’an dangɔɔne. Ba wan le ita laɣesegɔ n boi de to’ore kalam.

May 14, 2019​—Gã’aregɔ Zɛ’an B

Mabiisi n boi bim sɛla tiisi dangɔɔne bimbine zuo.

May 14, 2019​—Gã’aregɔ Zɛ’an A

Members of the exteriors crew install a glass barrier, forming what is known as a Juliet balcony. These barriers protect the residents without blocking light or ventilation.

May 21, 2019​—Ɔfisi Tuuma Deo

Mabiisi n tuni bugum tuuma n boi bim kɛ̃’ɛsa bugum.

June 11, 2019​—Saazuo Bɔba Maalegɔ Deo

Using slitting shears, a member of the mechanical team cuts ventilation ducting to size.

June 17, 2019​—Ɔfisi Tuuma Deo

Mabiisi n seli tiisi ge maala sore. Gɔbega la dela dia la laɣesegɔ zɛ’an. Gã’aregɔ Zɛ’an A n boi pooren sa la.

June 24, 2019​—Gã’aregɔ Zɛ’an A

An engineer installs part of the fire sprinkler system.

July 9, 2019​—Ɔfisi Tuuma Deo

Mabiisi n boi bim maasena zɛ’an ti ba sele mɔɔrɔ. Pooren sa la, ba dekɛ la water-fed pole system pee ɔfisi takɔla.

July 9, 2019​—Saazuo Bɔba Maalegɔ Deo

Members of the finishes crew lay a self-leveling floor compound. They use a gauge rake to apply an even layer of the compound, and then they use spiked rollers to remove air bubbles.

July 24, 2019​—Ɔfisi Tuuma Deo

Members of the finishes crew lay the vinyl floor of the multipurpose dining room, auditorium, and events space. On the back wall, where the platform will be located, television screens have been mounted on acoustic panels.

July 26, 2019​—Saazuo Bɔba Maalegɔ Deo

Zuo itigɔ la nɔnnɔm deo la n lɛm vidiyo tuuma zɛ’an la, ti karpinta bɔna bim maala.

August 1, 2019​—Saazuo Bɔba Maalegɔ Deo

Carpenters install the track for demountable office partitions. These partitions allow departments to reconfigure office space easily.

August 1, 2019​—Saazuo Bɔba Maalegɔ Deo

A contractor connects box trusses for rigging in the video studio. Rigging is used to suspend such equipment as lights and cameras when the studio is in session.

August 15, 2019​—Tigere Yile La

Zɛ’an la n ani se’em saazuo bɔba. Gɔbega la, ba mɛ Gã’aregɔ Zɛ’ɛsi B, D, E, Ɛ la F la ba’asɛ. Teŋasoka la, ba pɔ̃ri ba mɛ Gã’aregɔ Zɛ’a A la ba’asɛ ge ba puɣum mɛ Ɔfisi Tuuma Deo la ba’asɛ mɛ. Zuɔ la, ba pɔ̃ri ba mɛ Teŋanɔɔrɛ Bɔba Maalegɔ Deo la Saazuo Bɔba Maalegɔ Deo la ba’asɛ mɛ. Ge ba kelum maala teŋa la mɛ.

August 26, 2019​—Ɔfisi Tuuma Deo

Mabiisi n boi bim kɛ̃’ɛsera tiles n ani wuu kuga la reception zɛ’an la. Paɣasi la n boi pooren sa la dela ba zi’irego zɛ’an ti wuntɛɛŋa da paara ba ge ti ba duusa sɛba ti ba nan kɛ̃’ɛsɛ la.